HOW TO COLD START UP PROCEDURE IN POWER PLANTS
All the following Protections must be taken before cold Start up. here you are going to know about cold start-up procedure.
Description of Activity |
Remarks |
A. POWER SUPPLY NORMALISATION |
|
A.1
All PTWs are closed and clearances from all concerned departments are
available. |
|
A.2
All electrical switchboards (11 kV, 3.3 kV, and 0.415 kV) are charged from
proper sources. |
|
A.3
Power supply (both AC & DC) is available to all HT & LT drives
(Fans, Pumps, Gates, Dampers and Valves etc.). |
|
A.4
220 V DC supply with battery back-up is available for control,
protection as well as all emergency drives. |
|
A.5
UPS supply with battery back-up is available for DCS panels,
instruments and other required areas. |
|
A.6
Power supply is available to cooler fans of GT, UT & ST. |
|
A.7
Emergency DG set is lined up and breakers are ‘READY to CLOSE’.
(Ensure auto-changeover operation and day tank level > 500 L). |
|
A.8
All LCI panels for ID fans are charged and ready. |
|
A.9
No electrical protection is operated and all protection relays in all
AC & DC switchboards are RESET. |
|
B. READINESS OF BOILER AND ITS AUXILIARIES |
|
B.1.
LINE UP
OF BOILER & OTHER ASSOCIATED SYSTEMS |
|
B.1.1
All PTWs are closed and clearances from all concerned departments are
available. |
|
B.1.2
Interlocks & Protection of all associated systems are checked and
found ok. |
|
B.1.3
Boiler and its associated systems are free from any foreign material. |
|
B.1.4
Unauthorized entry to all areas are prohibited. |
|
B.1.5
Fire Protection & Prevention System (Hydrant and Foam) in all
required areas is charged. |
|
B.1.6
SOX & NOX analyzers in stack are in service.
|
|
B.1.7
Ensure fly ash & bottom ash handling system is functional. |
|
B.1.8
Close all inspection doors, manhole and access doors as well as peep
holes. |
|
B.1.9
Line up Compressed air system with both
instrument & service air (Header Pressure is maintained at 6.0 - 6.5
kg/cm²) IAC 1A ( ) IAC 1B ( )
SAC 1A ( ) SAC 1B ( ) |
|
B.1.10
All retractable soot blowers (LRSB) & wall blowers are fully
retracted & in home position. |
|
B.1.11
Furnace Temperature Probe (FTP) are fully retracted & in home
position |
|
B.1.12
Check SADC operation for all elevations. |
|
B.1.13
Check ESP manholes are closed & inlet and outlet gates of all
passes are fully open and locked. |
|
B.1.14
Check all gates & dampers in flue gas path are open and gas path
is clear through air heater A & B, ESP passes A, B, C & D. |
|
B.1.15
Ensure all hopper heaters, shaft & support insulator heaters of
ESP are charged. |
|
B.1.16
Ensure lube oil tank levels for ID, FD, PA, APH & Mills are normal |
|
B.1.17
Ensure all filter elements (all lube oil skids) are cleaned. |
|
B.1.18
Ensure Oil carry over probe of both APHs is in service and its Cooling
system available |
|
B.1.19
Line up CW system with its chemical dosing and chlorination system is
available. |
|
B.1.20
Start Circulating Water Pumps (2 nos.) taking
condenser A & B and IDCT cells in line. Ensure 18 cell riser valves are
open. (Ensure fore
bay level ≈ 7600-8000 mm) A (
) B ( ) |
|
B.1.21
Start ACW pumps (2 out of 3). A ( )
B ( ) C (
) |
|
B.1.22
Check availability of proper quality and sufficient quantity of DM
water. (Check level of DM water in DM storage tanks, CST, DMCW O/H tank and
Emergency filling tank etc.) CST > 5 m. |
|
B.1.23
Ensure raw water reservoir level and if required take make up by
intake pump. |
|
B.1.24
Ensure plant water make up pumps are ready with sufficient sump level.
Also ensure pre-treatment & RO-DM plant is fully functional. (Make up water sump Level ≈ mm). |
|
B.1.25
Start SG Equipment cooling water pump (1 out of
2). A ( )
B ( ) |
|
B.1.26
Check PHEs (2 nos.) for SG and auxiliaries are charged from both ACW
& DMCW. A ( ) B (
) |
|
B.1.27
Cavity of all BCW Pumps are filled; purged and proper water quality
(conductivity) is assured. |
|
B.1.28
HP & LP Cooling Line of all BCW Pumps are charged & pumps are
READY to start. (Check for LP cooling water flow ≈ >40 m3/Hr
for heat barrier and >160m3/Hr for Cavity cooler.)
Flow in Heat Barrier Cooler
Flow in LP Cavity Cooler BCW A BCW B BCW C |
|
B.1.29
Fill the water in the bottom ash hopper and seal trough and ensure
refractory cooling water line is lined up. |
|
B.1.30
Instrument air with pressure 6.0-6.5 kg/cm2 is available to
all corners of oil firing elevations (HEA igniters, Actuators in firing skid
etc.) |
|
B.1.31
Service air with pressure 6.0-6.5 kg/cm2 is available to
boiler area for LDO atomizing. |
|
B.1.32
LOTV (in LDO station, 26 mtr. Boiler elevation) as well as HOTV (in
HFO station, 26 mtr Boiler elevation) is fully closed. |
|
B.1.33
All manual isolation valves of firing skids are fully open and
pneumatic actuators (nozzle valves of air & oil line) are fully closed
position. |
|
B.1.34
Verify proper operation of all the instruments (gauges, transmitters
and recorders). Check all root valves in impulse lines are fully open. |
|
B.1.35
Ensure readiness of Coal Mills |
|
B.1.36
All LP/HP dosing pumps are ready. (Check for adequate level of N2H4,
NH3, Na2PO4 and Na3PO4
tanks) |
|
B.1.37
All Sampling lines (SWAS, Boiler, Coal, DM Water etc.) are ready. |
|
B.2.
OPEN THE
FOLLOWING |
|
B.2.1 Drum Vents (B-1, B-2, B-3, B-4, B-25, B-26, B-28 and B-29). |
|
B.2.2 CRH line
drain valves (CRHV-103, CRHV-104,
CRHV-178, CRHV-179, CRHV-180, CRHV-181, CRHV-182 and CRHV-183). |
|
B.2.3 HRH line
drain valves (HRHV-135, HRHV-136,
HRHV-137 and HRHV-138). |
|
B.2.4 HRH
strainer drains (HRHP-10 and HRHP-15). |
|
B.2.5
MS
strainer drains (MSV-105 & MSV-106) |
|
B.2.6 CRH line
vents (CRHV-105, CRHV-106, CRHV-107 and
CRHV-108). |
|
B.2.7 CRH line
vents (HRHV-117, HRHV-118, HRHV-119 and
HRHV-120). |
|
B.2.8 FSH
outlet vent isolation valves (S-31 and
S-32). |
|
B.2.9 MS line
vents (MSV-113, MSV-114, MSV-115 and
MSV-116). |
|
B.2.10 MS line
ERVs (SV-10 and SV-11) Manual
Isolation Valves. |
|
B.2.11 HRH line
ERVs (SV-22 and SV-23) Manual
Isolation Valves. |
|
B.2.12
SH
start-up vent isolation and regulating valves (S-34, S-35, S-36 and S-37). |
|
B.2.13 SH Header
drains (S-64, S-65, S-67, S-68, S-69,
S-70, S-71, S-72, S-73, S-74, S-75, S-76 and S-77) till 2kg/cm2
drum pressure. |
|
B.2.14 All
instrument and control valve connection to the boiler. |
|
B.2.15
Drum CBD
isolation valve. (B-83, B-84, B-86,
B-87 and B-89). |
|
B.2.16
SH drain
header to IBD tank isolation valve (S-78)
till 2 kg/cm². |
|
B.2.17
Main steam
line drain valves (MSV-101, MSV-102)
|
|
B.2.18
HP dosing
isolation valves (B-47 and B-48) |
|
B.2.19
Eco
Recirculation Valve (E-15) |
|
B.3.
CLOSE THE
FOLLOWING |
|
B.3.1. Economizer
inlet header line drain isolation valve (E-20). |
|
B.3.2. Boiler
filling valve (B-101) |
|
B.3.3. SH
filling line isolation valve (S-79) |
|
B.3.4. De –
Super heater control valve and supply valve. |
|
B.3.5. Drum CBD to
IBD tank MIV ( ) |
|
B.3.6. Chemical
injection valve depends on PH and conductivity. (B-47, B-48) |
|
B.3.7. Drum N2
filling isolation. (B-5, B-27) |
|
B.3.8. Drum
level gauge drain valve. (B-37, B-38, B-33, B-32, B-27, B-5) |
|
B.3.9. Main
steam line stop valve (MSV-1, MSV-2). |
|
B.3.10. Oil
burner valve and atomizing air valve to IBD. |
|
B.3.11. FSH N2
filling valve. |
|
B.3.12. Economizer
drain isolation valve after the drum is filled up to 4 ports. (E-17,E-18) |
|
B.4.
COOLING
WATER AND LUBRICATION SYSTEM LINE UP |
|
B.4.1. Start one
lube oil pump for each drive (IDF, FDF, PAF, APH, Coal mills) and keep
another pump on Auto Standby. |
|
B.4.2. Lube oil
tank heaters for Coal mills are on auto cut in/cut off mode |
|
B.4.3. Proper
lubrication (grease or oil) in each HT & LT drive with coupled fan or
pump (FDF, IDF, PAF, Seal air, Scanner fan, Air Compressors, BCWP, SG-DMCWP,
CWP, ACWP, Boiler fill pump, CT Pump and LDO F/W pump etc.). Check bearing oil
level in view glass and apply grease where ever required. |
|
B.4.4. SG DMCW
is available for lube oil cooling of all boiler auxiliary drives (FDF, IDF,
PAF, APH, Air Compressors, BCWP, and Coal Mills). |
|
B.4.5. SG DMCW
is available for motor winding cooling of large motors (ID Fan & PA Fan). |
|
B.4.6. Line up
cooling & lubrication system for fly ash & bottom ash disposal system. |
|
B.4.7. Ensure
proper lubrication (grease or oil) in all servo and pneumatic drives for
valves, dampers & gates. |
|
B.5.
FUEL OIL
LINE UP (F/O Pump House) |
|
B.5.1 Fuel oil
pump house and tank farm area is properly clean & no trace of oil leakage
is observed. |
|
B.5.2 Ensure
adequate oil in LDO storage tank. (Level >1.5 mtr. and Volume >170 m3) |
|
B.5.3 Drain oil
pump and sump pumps are in service |
|
B.5.4 Oil water
separator (OWS) system is fully functional. |
|
B.5.5 All
instruments are in service. |
|
B.5.6 Open the
manual isolation valves in suction line of LDO pumps. |
|
B.5.7 Check for
instrument air supply availability for pneumatic valves. |
|
B.5.8 Check LDO
short recirculation valve is in AUTO. |
|
B.5.9 Start one
LDO forwarding pump with other one standby available. Working A ( )
B ( ) Standby A (
) B ( ) |
|
B.6.
OIL
FIRING ARRANGEMENT LINE UP |
|
B.6.1 Check oil
station, oil firing skid area is free from any leakage and are properly
clean. |
|
B.6.2 Service
and instrument air is available to each elevation corners. |
|
B.6.3 All oil
guns and nozzles are clean. |
|
B.6.4 Burner
tilt operation is OK from DCS. Burner tilting is in horizontal or 0°C. |
|
B.6.5 All root
valves in impulse lines are fully open and equipment’s (Flow-meter, Pressure
gauges, temp gauges etc.) at LDO station (Boiler area) are in service. |
|
B.6.6 Oil firing
skids on each elevation corner are in service. |
|
B.6.7 All oil
guns are properly inserted and coupled. |
|
B.6.8 All oil
guns and their associated piping are ready for service. |
|
B.6.9 All
manual valves are open and control valves are closed. |
|
B.6.10 Service
Air available for ignitor cooling |
|
B.6.11 AC
Scanner Air Fan is in service with emergency backup of DC scanner air fan and
air available to scanner and oil gun tip cooling. |
|
B.7.
PULVERISERS
(COAL MILL) LINE UP |
|
B.7.1 Check all
permissive are available. |
|
B.7.2 Check Bunker level ( ). |
|
B.7.3 Discharge
valves of all mills (MDV) are open. |
|
B.7.4 One seal
air fan is running; A (
) B ( ) seal air
isolation valve is open & seal air is supplied to all mills &
gravimetric feeders. |
|
B.7.5 Check
operation of HAG, CAG, HAD & CAD of all mills from DCS |
|
B.7.6 Hot air
gate and hot air control dampers are fully closed |
|
B.7.7 Bunker
outlet gates and Feeder inlet gates are open and coal is available to
gravimetric feeders. (Check through view glass for coal on feeder belt) |
|
B.7.8 All
classifier vanes settings are identical. |
|
B.8.
BOILER
INITIAL FILLING |
|
B.8.1 Ensure
for proper quantity of DM water in CST (Level > 5 mtr.) |
|
B.8.2 Check all
vent valves of economizer, boiler drum and super heaters are open. |
|
B.8.3 Open
following valves. B-101 – Isolation Valve in Boiler filing line B-98, B-99 – Bottom Ring Header drain E-15, E-16 – Eco filling line drain E-17, E-18 – Eco Header drain E-13, E-14 – Eco recirculation line |
|
B.8.4 Close
following valves. B-96, B-97
– Bottom Ring header front side drain to IBD tank |
|
B.8.5 Start the
boiler fill pump. |
|
B.8.6 Fill
water in boiler drum up to normal operating level. (5 port, +100 mmwc) |
|
C. READINESS OF TURBO-GENERATOR AND ITS AUXILIARIES |
|
C.1
LINE UP
OF TURBOGENERATOR & OTHER ASSOCIATED SYSTEMS |
|
C.1.1
All PTWs are closed and clearances from all concerned departments are
available. |
|
C.1.2
Interlocks & Protection of all associated systems are checked and
found ok. |
|
C.1.3
TG and its associated systems are free from any foreign material. |
|
C.1.4
Unauthorized entry to all areas are prohibited. |
|
C.1.5
Fire Protection & Prevention System (Hydrant & Spray &
Inert Gas System) in all required areas is charged. |
|
C.1.6
Check all valves of cooling water, condensate, feed water lines and
turbine & generator auxiliaries are fully functional. |
|
C.1.7
All hydraulic skids for control valves are ready in all aspects and no
oil leakage is observed. |
|
C.1.8
Ensure TWO CW pump and two ACW pumps are in service. |
|
C.1.9
Start TG equipment cooling water pumps (TG-DMCW)
(2 out of 3). A ( ) B (
) C ( )
|
|
C.1.10
2 nos. PHEs for TG area are in service (keep 3rd one in
standby) and charged from both DMCW & ACW. A ( )
B ( ) C (
) |
|
C.1.11
Air compressors are in service and both instrument and service air are
available to all associated areas with adequate pressure (6.0 – 6.5 kg/cm2) |
|
C.1.12
Verify proper operation of all the instruments (gauges, transmitters
and recorders). Check all root valves in impulse lines are fully open. |
|
C.1.13
Ensure all strainer/filter elements (CEPs, BFPs, lube/seal/control oil
skids etc.) are properly cleaned by service air/replaced by a new one. |
|
C.1.14
Clean & dirty oil tanks are lined up with its centrifuge system in
service. |
|
C.2
OPEN THE
FOLLOWING |
|
C.2.1 CEP
suction valves (CSV-1, CSV-2 and CSV-3). |
|
C.2.2 Gland
steam condenser inlet & outlet valves (CDV-16, CDV-18). |
|
C.2.3 CPU
Bypass Valve (CDV-19). |
|
C.2.4 Condensate
control station valves (CDV-21, CDV-23,
CDV-24 and CDV-26). |
|
C.2.5 Drain
Cooler inlet valve (CDV-28). |
|
C.2.6 All LP
heaters inlet & outlet valves (CDV-31,
CDV-32, CDV-34 and CDV-35). |
|
C.2.7 Inlet
valve of Deaerator (CDV-48). |
|
C.2.8 All MIVs
of connection link between FST & stand pipe. |
|
C.2.9 Deaerator
Overflow line valves (DRV-45, DRV-47
and DRV-50). |
|
C.2.10 BFP
suction valves (FSV-1, FSV-2 and FSV-3). |
|
C.2.11 BFP recirculation
valve (FCV-1, FCV-2 and FCV-3). |
|
C.2.12 Feed
Regulating Station valves (FDV-13 and
FDV-15). |
|
C.2.13 Feed
Water Line Valves (FDV-7, FDV-8, FDV-9
and FDV-10). |
|
C.2.14 Hot-well
make up valves (DMV-32, DMV-34, DMV-35, DMV-37, DMV-40, DMV-42, DMV-43 and
DMV-45). |
|
C.2.15 Minimum
flow recirculation line valves (CDV-38,
CDv-40, CDV-204 and CDv-205) |
|
C.2.16 Condenser
vacuum pump line valves (SMV-23,
SMV-24, SMV-25, SMV-26, SMV-37, SMV-28, SMV-29 and SMV-30). |
|
C.3
CLOSE THE
FOLLOWING |
|
C.3.1 CEP
discharge valves (CDV-4, CDV-5 and
CDV-6). |
|
C.3.2 CPU inlet
and outlet valves () |
|
C.3.3 Condensate
line valves (CDV-74, CDV-27, CDV-30,
CDV-33 and CDV-36). |
|
C.3.4 Deaerator
Overflow line valve (DRV-49). |
|
C.3.5 Condensate
line drain isolation valves (CDV-101,
CDV-102, CDV-103, CDV-108, CDV-109, CDV-110, CDv-112, CDV-119, CDV-123, CDV-125,
CDV-127, CDV-128, CDV-129, CDV-139 and CDV-140). |
|
C.3.6 BFP
discharge valves (FDV-4, FDV-5, FDV-6
and respective IBVs). |
|
C.3.7 Feed
water regulating valve (FDV-14 and
FDV-16). |
|
C.3.8 RH &
APRDS Spray Valve (FDV-18, FDV-20 and
FDV-22) |
|
C.3.9 Feed
Water Line Valves (FDV-11 and FDV-12;
HP Heater 5 & 6 Bypass Isolators). |
|
C.3.10 Feed
Water line drain isolation valve (FDV-129
and FDV-130). |
|
C.4
COOLING WATER AND
LUBRICATION SYSTEM LINE UP |
|
C.4.1 TG DMCW
is available for motor winding cooling of MDBFP. |
|
C.4.2 TG DMCW
is available for cooling of bearings & mechanical seals of TG auxiliary
drives (BFP, CEP etc.) |
|
C.4.3
Cooling water is charged for oil coolers of turbo-generator lube oil
and control oil system, generator seal oil system, BFP (MD & TD) lube oil
& control oil system. |
|
C.4.4
Charge cooling water for Hydrogen Cooler and Exciter Cooler and do
venting. |
|
C.4.5 Line up lube oil system of main turbine-generator
set |
|
C.4.5.1 Check oil
level in MOT is normal; note down level |
|
C.4.5.2 Note down
lube oil filters chocking with standby one cleaned |
|
C.4.5.3 Line up
lube oil coolers, filters and start AOP (Put SLC ON for AOP & EOP; check
auto start of AOP and EOP) |
|
C.4.5.4 Check
auto pickup of DCEOP and keep its SLC on |
|
C.4.5.5 Put Lube
oil temperature controller ON. (Maintain temp. 45˚C) |
|
C.4.5.6 Start one
JOP keeping other one ready for standby (Put SLC ON for other JOPs; check
auto-start of other JOPs). |
|
C.4.5.7 Open gate
valve of turning/barring gear. (Switch on SLC for gate valve of turning gear) |
|
C.4.5.8 Take TG on barring gear. (RPM
approx. 80 rpm without condenser vacuum) |
|
C.4.6 Line up lube/control oil system of Boiler Feed
Pumps (1 MD & 2 TD) |
|
C.4.6.1 Check oil
level is normal in hydraulic coupling for MDBFP and in Oil storage tanks for
TDBFPs. Note down levels. |
|
C.4.6.2 Check
barring gear valve is opened and valve selection in remote |
|
C.4.6.3 Check
auto startup of DC EOP. |
|
C.4.6.4 Lube oil
temp control valve of TDBFP is in auto and maintain 45˚C temp |
|
C.4.6.5 Line up
lube oil coolers, filters and start one lube oil pump keeping other one ready
on auto standby. |
|
C.4.6.6 Take
TDBFPs on barring gear (Speed approx. 340 rpm) |
|
C.4.6.7 Check
Control oil supply MIV open & pressure available 9 kg/cm2 |
|
C.4.7
Ensure proper lubrication (grease or oil) in all servo and pneumatic
drives for valves. |
|
C.5
CONTROL
OIL SYSTEM LINE UP FOR MAIN TURBINE |
|
C.5.1 Check CF
tank level is normal. Note down the level |
|
C.5.2 Start one
CF pump; put SLC on & check auto start of second pump. |
|
C.5.3 Establish
control fluid supply to governing skids. (FRF tank level ‘0’ mm - normal
level) |
|
C.5.4 Start one
control fluid Vapour Extractor fan. |
|
C.5.5 Start one
recirculation pump by taking filters (fine & ultrafine) in service. |
|
C.5.6 Switch on
FRF heater and keep SLC ON for temperature control & control fluid pumps.
(Maintain FRF tank temp 50°C) (Ensure temperature increase gradient range
1-2°K/Hr.) |
|
C.5.7 Keep temp
control valve in AUTO. |
|
C.5.8 Ensure control
oil system SGC is ON. |
|
C.5.9 Ensure all valve rack filters are clean & EHTC is
lined up. |
|
C.6
GENERATOR
AUXILIARIES LINE UP |
|
C.6.1 Generator
protection panel and Excitation system is ready. |
|
C.6.2 Ensure
cooling system is ready for gas system, primary water system, seal oil
system, exciter-stator-rotor winding. Put Temp Control valves for gas and
primary water in auto. |
|
C.6.3 Check
primary water tank level. Note down the level |
|
C.6.4 Start one primary water pump keeping other one
standby (Keep SLC PW system ON). Running pump A ( ) B (
) |
|
C.6.5 Ensure
NaOH dosing pump in auto and primary water conductivity after main filter
(1-2.5 μS/cm) and pH > 7. |
|
C.6.6 Note down
N2 pressure in PW tank (if <0.25 ksc,
refill from gas room) |
|
C.6.7 Start one
generator bearing vapour exhauster fan. (keep another on standby) |
|
C.6.8 Ensure one AC seal oil pump ON &other AC
& DC pumps on standby (Keep SLC of AC SOP & DC SOP ON); check auto
start of other pumps. Ensure seal oil and ring relief oil supply to generator
bearings are established. Running
Pump A ( )
B ( ) |
|
C.6.9 Note down
no of H2 cylinders and CO2
cylinders available in
gas room |
|
C.6.10 Ensure generator is filled with hydrogen with
pressure in generator > 3.5 kg/cm2 and gas-air purity > 98%. |
|
C.6.11 Check LLD
rack is free from oil and drain connected to waste fluid system |
|
C.7
Condensate
and Feed water System Line Up |
|
C.7.1 Line up condensate
path from hot-well A & B up to Deaerator taking all LP heaters, gland
steam condenser and drain cooler in line. |
|
C.7.2 Ensure
condensate polishing unit is bypassed. |
|
C.7.3 Start
condensate transfer pumps to maintain hot-well level +900 mmwc through
hot-well make up station. |
|
C.7.4 Line up
feed water path from FST up to economizer through all HP heaters. |
|
C.7.5 Start CEPs (2 out of 3) in recirculation keeping
other one ready to start on standby Running
Pump A ( )
B ( ) C (
) |
|
C.7.6 Valve gland seal station is charged with pressure control
valve in auto. Maintain pressure > 3ksc |
|
C.7.7 Maintain
Deaerator level (+100 mmwc) by controlling condensate control
station valves (CDV-22 & CDV-25). |
|
C.7.8
Start
AOP of MDBFP. |
|
C.7.9 Start MDBFP with recirculation valve 100% open, discharge valve fully
closed and scoop minimum (Maintain Deaerator level normal) (Ensure
cooling, sealing and lube oil lines are charged) |
|
C.7.10 Ensure
RH, APRDS and HPBP spray valves are closed. |
|
C.7.11 Open
discharge valve and charge feed water up to feed control station. (Ensure FDV-14 & FDV-16 are fully closed). |
|
C.7.12 Start
ammonia and hydrazine dosing. Before boiler light up feed
water parameters should be:
Conductivity: 0.65µg/cm, pH: 9.0-9.6, SiO2: ≤30ppb, Fe: ≤50ppb,
Cu: ≤15ppb, Na: ≤20ppb, N2H4: 10-50µg/L |
|
Post a Comment